Re: Is a USB to GPIB dongle/convertor a difficult project ?



Michael A. Terrell wrote:
Joerg wrote:
Most places I've seen operate in similar fashion. But you know how it
goes. The guy with the floor buffer comes along, dragging that big power
cable. Leroy wants to quickly finish up what the night shift didn't
quite get done, he's a bit tired by now, rolls the cart with the heavy
analyzer, oops ...


The maintenance man was a full time day shift employee, and wasn't
allowed to move any equipment if the tech wasn't at the bench. There was
no second or third shift, just some overtime for the day shift people.
Most of the carts had so many cables run to the bench that they had to
be unhooked to move more than a few inches. We were notified of any
building maintenance, so if you needed the floor cleaned under your
bench, you unhooked everything and rolled it to the wall, in an are that
would be cleaned the following Saturday. I'm not trying to argue with
you, but the system can work well, with proper planning.

We eliminated carts, were possible, but some techs had over 50 pieces
of test equipment on their benches. We were an engineering to order
facility, and priorities could change a couple times a day, if a
customer's plans changed. We also built and tested some base chassis
for stock, for emergency orders. We were able to ship a couple custom
radios within three days, to replace equipment that was damaged at a
customer's site.


The businesses I usually work at are very different. Full-bore production with expensive machinery. So you have to maximize runtimes, up to about 20hrs/day with the remainder being used for PM. Often two 10h shifts. PM was also going around the clock from machine to machine. So the maintenance guys didn't have a chance other than interfering a bit. Including the guy with that big tile buffer ...

--
Regards, Joerg

http://www.analogconsultants.com/

"gmail" domain blocked because of excessive spam.
Use another domain or send PM.
.



Relevant Pages

  • Re: Is a USB to GPIB dongle/convertor a difficult project ?
    ... The guy with the floor buffer comes along, ... The maintenance man was a full time day shift employee, ... allowed to move any equipment if the tech wasn't at the bench. ... Most of the carts had so many cables run to the bench that they had to ...
    (sci.electronics.equipment)
  • Re: Mercruiser i/o will not go into neutral
    ... > All correct except the shift engine kill switch SHOULD engage if there is ... but when the control cable and lower shift cable are in good ... > because the engine is running faster than the prop. ... or misadjusted cables, or a simulated shift load caused by resistance ...
    (rec.boats)
  • Re: Mercruiser i/o will not go into neutral
    ... >> All correct except the shift engine kill switch SHOULD engage if there is ... >> because the engine is running faster than the prop. ... Bending the shift cables by having the outdrive at extreme angles ...
    (rec.boats)
  • Re: Mercruiser i/o will not go into neutral
    ... >>> All correct except the shift engine kill switch SHOULD engage if there is ... >>> because the engine is running faster than the prop. ... Bending the shift cables by having the outdrive at extreme angles ...
    (rec.boats)
  • Re: shift interrupt switch
    ... box attaches and also the cable to the lower unit attaches as well as the ... This is where the shift interrupter is located. ... Usually the best solution is to replace both of the cables and the shift ... special tool to install the threaded end on the lower unit end, ...
    (rec.boats)