Re: Air Force Signs Off on SRB-CEV
- From: "Ed Kyle" <edkyle99@xxxxxxxxxxx>
- Date: 15 Aug 2005 10:22:04 -0700
Kim Keller wrote:
> "Ed Kyle" <edkyle99@xxxxxxxxxxx> wrote in message
> news:1123908436.663883.31440@xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
> > How about the GAO's numbers?
> > "http://www.gao.gov/htext/d04778r.html"
> >
> > They say that EELV "Program and launch costs increased
> > by about $13.3 billion over the approved 2002 baseline
> > estimate of $18.8 billion". That's a 71% increase,
> > over the original EELV contract when a straight EELV
> > sold for something in the $70 million range, which
> > puts both straight EELV models up to the $120 million
> > plus range today. The GAO report says that the EELV
> > program is getting close to costing as much as
> > Titan IV.
>
> Don't forget that prices will come down as orders go up. NASA has been
> launching roughly four space science missions per year on Delta II. Take
> those orders and insert them in the EELV companies' order books and see what
> the price drops to.
Since the EELVs duplicate each other's capabilities
and not those of Delta II, why not keep Delta II
and drop one of the EELVs instead? I bet DoD
would save a lot more cash that way.
- Ed Kyle
.
- Follow-Ups:
- Re: Air Force Signs Off on SRB-CEV
- From: George William Herbert
- Re: Air Force Signs Off on SRB-CEV
- References:
- Air Force Signs Off on SRB-CEV
- From: Ed Kyle
- Re: Air Force Signs Off on SRB-CEV
- From: Kim Keller
- Re: Air Force Signs Off on SRB-CEV
- From: Ed Kyle
- Re: Air Force Signs Off on SRB-CEV
- From: Kim Keller
- Re: Air Force Signs Off on SRB-CEV
- From: Ed Kyle
- Re: Air Force Signs Off on SRB-CEV
- From: Kim Keller
- Air Force Signs Off on SRB-CEV
- Prev by Date: Re: Deep Impact Kicks Off Fourth of July with Deep Space Fireworks
- Next by Date: Re: Shuttle Replacement Needs to Become a National Priority!!!
- Previous by thread: Re: Air Force Signs Off on SRB-CEV
- Next by thread: Re: Air Force Signs Off on SRB-CEV
- Index(es):
Relevant Pages
|